The MTENTU Bridge project in South Africa has a total length of 1.13 kilometers and adopts a multi-span concrete box girder structure. The span layout of the bridge is 53.7+5×66+150+260+150+2×66+53.7 meters. The project contract amount is 230 million US dollars, and the construction period is 54 months, including a 4-month mobilization period.
Suppliers are determined through the community public bidding model and are determined after obtaining the approval of the supervisor and the owner. The supply area is the mixing plant on the north bank of the project. The quotation is a floating price and is quoted based on the model of processing plant + profit, including material cost, transportation cost, loading and unloading, and profit, etc
|
1
|
||
|
2
|
|
1
|
普通硅酸盐水泥 P﹒O 32.5 散装
|
2000.****0000
|
吨
|
|
|
2
|
普通硅酸盐水泥 P﹒O 52.5 散装
|
10000.****0000
|
吨
|
|
|
3
|
混凝土用磨细矿渣
|
7000.****0000
|
立方米
|