洮南市洮儿河(含蛟流河)防洪薄弱环节治理工程

审批
吉林-白城-洮南市
发布时间: 2025年12月22日
项目详情
下文中****为隐藏内容,仅对千里马会员开放,如需查看完整内容请 或 拨打咨询热线: 400-688-2000
1、建设项目基本信息
企业基本信息
建设单位名称: 建设单位代码类型: 建设单位机构代码: 建设单位法人: 建设单位联系人: 建设单位所在行政区划: 建设单位详细地址:
****
2301-220881-04-01-820464白凤仁
王红叶**省**市**市
**省**市**市
建设项目基本信息
项目名称: 项目代码: 项目类型: 建设性质: 行业类别(分类管理名录): 行业类别(国民经济代码): 工程性质: 建设地点: 中心坐标: ****机关: 环评文件类型: 环评批复时间: 环评审批文号: 本工程排污许可证编号: 排污许可批准时间: 项目实际总投资(万元): 项目实际环保投资(万元): 运营单位名称: 运营单位组织机构代码: 验收监测(调查)报告编制机构名称: 验收监测(调查)报告编制机构代码: 验收监测单位: 验收监测单位组织机构代码: 竣工时间: 调试起始时间: 调试结束时间: 验收报告公开起始时间: 验收报告公开结束时间: 验收报告公开形式: 验收报告公开载体:
**市洮儿河(含蛟流河)防洪薄弱环节治理工程
2021版本:127-防洪除涝工程E4822-E4822-河湖治理及防洪设施工程建筑
**省**市**市
经度:122.28315,122.2856,122.28616,122.29419,122.2975,122.29925,122.30193,122.30248,122.3032,122.30662,122.30573,122.30927,122.33019,122.34633,122.35071,122.35838,122.36375,122.36832,122.36864,122.37184,122.37302,122.37442,122.37688,122.37727,122.38774,122.40098,122.40469,122.4087,122.41227,122.41358,122.41894,122.42063,122.42418,122.42501,122.42593,122.426,122.4425,122.44797,122.44741,122.44829,122.44999,122.45119,122.4529,122.45388,122.45485,122.45687,122.45847,122.4596,122.46046,122.46089,122.4645,122.46458,122.46376,122.46507,122.46544,122.46606,122.46786,122.46812,122.46782,122.46887,122.46855,122.47031,122.47276,122.47404,122.47385,122.47449,122.476,122.47499,122.47924,122.48198,122.48233,122.48404,122.48666,122.48821,122.49267,122.49623,122.4972,122.49722,122.49681,122.4981,122.49907,122.49984,122.50104,122.50129,122.49971,122.50211,122.50295,122.50364,122.5037,122.5043,122.50496,122.50604,122.50752,122.51026,122.51217,122.51363,122.51601,122.51674,122.51754,122.52093,122.52224,122.5249,122.52501,122.52716,122.52812,122.53097,122.53266,122.53453,122.53885,122.54041,122.54205,122.54219,122.54173,122.54194,122.54183,122.54253,122.54411,122.5467,122.54908,122.54771,122.54687,122.5459,122.54578,122.54475,122.54634,122.54811,122.54982,122.54973,122.54786,122.546,122.54424,122.54381,122.54606,122.54579,122.54611,122.5464,122.54597,122.54625,122.53976,122.54018,122.5399,122.54058,122.54056,122.53923,122.53983,122.5482,122.55045,122.55202,122.55863,122.55942,122.56183,122.56378,122.56451,122.5656,122.56569,122.56951,122.57565,122.58069,122.58243,122.58539,122.58586,122.59296,122.59891,122.60051,122.6032,122.61193,122.61588,122.61974,122.6209,122.62199,122.62418,122.62787,122.6294,122.63154,122.63399,122.63641,122.64206,122.64491,122.65075,122.65319,122.65725,122.67214,122.67251,122.67368,122.67555,122.67588,122.67806,122.67896,122.68722,122.69064,122.69207,122.69306,122.69931,122.70373,122.70473,122.71132,122.7128,122.71441,122.71589,122.71703,122.71825,122.71941,122.71986,122.72061,122.72254,122.72338,122.72426,122.7239,122.73203,122.73338,122.74168,122.7428,122.74411,122.74389,122.74593,122.74823,122.75149,122.75239,122.75539,122.76102,122.76241,122.76179,122.76205,122.76173,122.76282,122.76402,122.76634,122.76934 纬度: 45.66738,45.66742,45.66339,45.66025,45.66001,45.66041,45.6598,45.65839,45.65777,45.65763,45.6542,45.65261,45.64467,45.63566,45.63236,45.62867,45.62553,45.62384,45.62292,45.62182,45.62197,45.62071,45.61747,45.61656,45.61341,45.60356,45.59991,45.60032,45.60262,45.60305,45.60371,45.60382,45.60318,45.60167,45.60047,45.59893,45.58998,45.58524,45.58399,45.58333,45.58316,45.58361,45.58331,45.58316,45.58231,45.58175,45.58155,45.58079,45.57976,45.57801,45.57399,45.57288,45.57148,45.56874,45.56695,45.56629,45.56365,45.56316,45.56193,45.56011,45.55848,45.55556,45.55402,45.55108,45.55039,45.54949,45.54889,45.54745,45.54393,45.54121,45.53992,45.53872,45.53554,45.53305,45.53252,45.52994,45.52779,45.52664,45.5262,45.52445,45.52434,45.52296,45.51722,45.51586,45.51492,45.51063,45.51035,45.50966,45.50831,45.5076,45.5026,45.50177,45.49938,45.4981,45.49602,45.49318,45.49123,45.48988,45.48971,45.49074,45.49082,45.48814,45.4871,45.4856,45.48407,45.48149,45.47966,45.47925,45.47925,45.47855,45.47712,45.47596,45.47498,45.47412,45.47256,45.47154,45.47088,45.47005,45.46544,45.46402,45.46404,45.46344,45.46297,45.46237,45.45992,45.45928,45.45601,45.45474,45.4532,45.45271,45.45139,45.44793,45.44335,45.44293,45.44083,45.44053,45.43843,45.43735,45.43646,45.4292,45.42793,45.42566,45.42445,45.42282,45.42059,45.41396,45.41355,45.41422,45.41325,45.41278,45.41304,45.41109,45.4083,45.40679,45.40544,45.40441,45.40115,45.40096,45.40122,45.39858,45.39718,45.39109,45.38707,45.38534,45.38624,45.38654,45.38577,45.3816,45.38062,45.38032,45.37834,45.37351,45.37193,45.37045,45.36999,45.37004,45.36785,45.36972,45.36871,45.3683,45.36993,45.36564,45.36489,45.365,45.36422,45.36349,45.36233,45.36237,45.36145,45.36021,45.36111,45.36251,45.36302,45.36175,45.36212,45.36225,45.36184,45.36206,45.36064,45.36042,45.36057,45.36027,45.35976,45.35991,45.35952,45.35766,45.35643,45.35527,45.35403,45.35439,45.35491,45.35542,45.35699,45.35905,45.36025,45.36092,45.36263,45.36351,45.36469,45.36592,45.36435,45.36351,45.36296,45.36212,45.3598,45.35884,45.35671,45.35369****环境局****分局
2023-09-13
洮环行审字〔2023〕9号
10181.34
164.1164****
112********595971X****
112********595971X**省****公司
****0000MA17A48L3A2025-10-31
2025-11-242025-12-19
https://gongshi.****.com/h5public-detail?id=487255
2、工程变动信息
项目性质
环评文件及批复要求: 实际建设情况: 变动情况及原因: 是否属于重大变动: 是否重新报批环境影响报告书(表)文件:
****
无变动
规模
环评文件及批复要求: 实际建设情况: 变动情况及原因: 是否属于重大变动: 是否重新报批环境影响报告书(表)文件:
本项目建设内容主要为**堤防1.476km;堤防加高培厚49.996km;上堤坡道77条总长15.4km;错车道4处长度30m;修建穿堤建筑物5座,其中**排水闸3座,拆除**排水闸2座;险工护岸12处,护岸长度5.615km。本项目建设内容主要为**堤防1.476km;堤防加高培厚49.996km;上堤坡道77条总长7.5km;错车道4处长度30m;修建穿堤建筑物5座,其中**排水闸3座,拆除**排水闸2座;险工护岸12处,护岸长度7.187km。
上堤坡道长度减少7.9km,险工护岸长度增加1.572km
生产工艺
环评文件及批复要求: 实际建设情况: 变动情况及原因: 是否属于重大变动: 是否重新报批环境影响报告书(表)文件:
本项目为防洪薄弱环节治理工程。本项目运营期无任何污染物产生本项目为防洪薄弱环节治理工程。本项目运营期无任何污染物产生
无变动
环保设施或环保措施
环评文件及批复要求: 实际建设情况: 变动情况及原因: 是否属于重大变动: 是否重新报批环境影响报告书(表)文件:
对取土场区、主体工程区进行表土剥离,其中表土层厚度为0.1-0.3m,剥离的表土临时堆放在取土场区内,对临时表土场采取加盖苫布和临时挡护措施,施工结束后进行表土回覆;排水闸施工时采取围堰施工方式进行。 ****施工队伍的环保意识;选用尾气达标排放的施工机械;控制施工车辆的数量;加强对运输车辆的管理;定期对施工设备、机械进行维护;封闭或加盖苫布运输:定期洒水降尘。废气排放浓度满足《大气污染物综合排放标准》(GB16297-1996)中二级标准及无组织排放标准。 施工期产生的废水及施工设备冲洗废水排入沉淀池,沉淀后上**回用。生活污水排入防渗旱厕,发酵后定期清掏还田。 尽量选用先进的低噪声设备;严格控制和管理施工时间、运输车辆行驶时间、行驶路线;限制老、旧施工机械数量;定期对施工设备进行维护;设置声屏障,在居民区附近施工时禁止夜间施工。噪声排放标准满足《建筑施工场界环境噪声排放标准》(GB12523-2011)中排放限值要求。 施工期产生的生活垃圾全部暂存于施工生产生活区内垃圾桶,定期送当地****填埋场。建筑垃圾尽量综合利用,现场无建筑渣土堆存,无二次污染。通过调查,本项目施工期均按照环评文件及批复要求进行施工,将土壤风蚀、水蚀影响降至最低程度;施工过程中已尽量减少对原有土地的损坏,施工前表土剥离,施工结束后进行植被恢复。 施工单位已加强施工管理,合理安排施工进度及时间,按照总体平面布置图施工,限制运输车辆的行驶速度,对路面及堆场要定时洒水抑尘,运输粉状材料的车辆应覆盖蓬布,控制施工车辆的数量等措施。 施工废水采用临时简易的沉淀处理后回用、浇洒路面,不外排;施工人员生活污水排入移动式防渗旱厕,定期清淘外运做肥料,厕所底部做严密防渗措施,雨季采取覆盖措施,施工时采用截流蓄水和管道导流相结合的方式,河水优先蓄水后用于生产用水,多余水量用管道导流至附近其他草地或下游沟道中。施工选择合理的时段实施。 施工运输车辆行驶时间、行驶路线进行严格控制和管理,避开噪声敏感区域和噪声敏感时段。加强施工噪声的管理,避免夜间施工。限制老、旧施工机械数量,及时维修噪声大的施工机械。设置禁鸣牌。临近村屯施工时居民一侧设置可移动声屏障。 建筑垃****填埋场处置;生活垃圾集中分类收集,定期送往当地环卫部门指定垃圾中转站,由环卫部门统一处理。散落的砂浆、混凝土,作为再生骨料回收利用;不可回收利用的废金属可回收后外售利用。
无变动
其他
环评文件及批复要求: 实际建设情况: 变动情况及原因: 是否属于重大变动: 是否重新报批环境影响报告书(表)文件:
//
/
3、污染物排放量
污染物 现有工程(已建成的) 本工程(本期建设的) 总体工程 总体工程(现有工程+本工程) 排放方式 实际排放量 实际排放量 许可排放量 “以新带老”削减量 区域平衡替代本工程削减量 实际排放总量 排放增减量 废水 水量 (万吨/年) COD(吨/年) 氨氮(吨/年) 总磷(吨/年) 总氮(吨/年) 废气 气量 (万立方米/年) 二氧化硫(吨/年) 氮氧化物(吨/年) 颗粒物(吨/年) 挥发性有机物(吨/年)
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0 /
0 0 0 0 0 0 0 /
0 0 0 0 0 0 0 /
0 0 0 0 0 0 0 /
0 0 0 0 0 0 0 /
4、环境保护设施落实情况
表1 水污染治理设施
序号 设施名称 执行标准 实际建设情况 监测情况 达标情况
表2 大气污染治理设施
序号 设施名称 执行标准 实际建设情况 监测情况 达标情况
表3 噪声治理设施
序号 设施名称 执行标准 实际建设情况 监测情况 达标情况
表4 地下水污染治理设施
序号 环评文件及批复要求 验收阶段落实情况 是否落实环评文件及批复要求
表5 固废治理设施
序号 环评文件及批复要求 验收阶段落实情况 是否落实环评文件及批复要求
表6 生态保护设施
序号 环评文件及批复要求 验收阶段落实情况 是否落实环评文件及批复要求
1 对取土场区、主体工程区进行表土剥离,其中表土层厚度为0.1-0.3m,剥离的表土临时堆放在取土场区内,对临时表土场采取加盖苫布和临时挡护措施,施工结束后进行表土回覆;排水闸施工时采取围堰施工方式进行。 本项目施工期均按照环评文件及批复要求进行施工,将土壤风蚀、水蚀影响降至最低程度;施工过程中已尽量减少对原有土地的损坏,施工前表土剥离,施工结束后进行植被恢复。
表7 风险设施
序号 环评文件及批复要求 验收阶段落实情况 是否落实环评文件及批复要求
5、环境保护对策措施落实情况
依托工程
环评文件及批复要求: 验收阶段落实情况: 是否落实环评文件及批复要求:
//
/
环保搬迁
环评文件及批复要求: 验收阶段落实情况: 是否落实环评文件及批复要求:
//
/
区域削减
环评文件及批复要求: 验收阶段落实情况: 是否落实环评文件及批复要求:
//
/
生态恢复、补偿或管理
环评文件及批复要求: 验收阶段落实情况: 是否落实环评文件及批复要求:
对取土场区、主体工程区进行表土剥离,其中表土层厚度为0.1-0.3m,剥离的表土临时堆放在取土场区内,对临时表土场采取加盖苫布和临时挡护措施,施工结束后进行表土回覆;排水闸施工时采取围堰施工方式进行。本项目施工期均按照环评文件及批复要求进行施工,将土壤风蚀、水蚀影响降至最低程度;施工过程中已尽量减少对原有土地的损坏,施工前表土剥离,施工结束后进行植被恢复。
/
功能置换
环评文件及批复要求: 验收阶段落实情况: 是否落实环评文件及批复要求:
//
/
其他
环评文件及批复要求: 验收阶段落实情况: 是否落实环评文件及批复要求:
//
/
6、工程建设对项目周边环境的影响
地表水是否达到验收执行标准: 地下水是否达到验收执行标准: 环境空气是否达到验收执行标准: 土壤是否达到验收执行标准: 海水是否达到验收执行标准: 敏感点噪声是否达到验收执行标准:
/
/
/
/
/
/
7、验收结论
序号 根据《建设项目竣工环境保护验收暂行办法》有关规定,请核实该项目是否存在下列情形:
1 未按环境影响报告书(表)及其审批部门审批决定要求建设或落实环境保护设施,或者环境保护设施未能与主体工程同时投产使用
2 污染物排放不符合国家和地方相关标准、环境影响报告书(表)及其审批部门审批决定或者主要污染物总量指标控制要求
3 环境影响报告书(表)经批准后,该建设项目的性质、规模、地点、采用的生产工艺或者防治污染、防止生态破坏的措施发生重大变动,建设单位未重新报批环境影响报告书(表)或环境影响报告书(表)未经批准
4 建设过程中造成重大环境污染未治理完成,或者造成重大生态破坏未恢复
5 纳入排污许可管理的建设项目,无证排污或不按证排污
6 分期建设、分期投入生产或者使用的建设项目,其环境保护设施防治环境污染和生态破坏的能力不能满足主体工程需要
7 建设单位因该建设项目违反国家和地方环境保护法律法规受到处罚,被责令改正,尚未改正完成
8 验收报告的基础资料数据明显不实,内容存在重大缺项、遗漏,或者验收结论不明确、不合理
9 其他环境保护法律法规规章等规定不得通过环境保护验收
不存在上述情况
验收结论 合格
温馨提示
1.该项目指提供国家及各省发改委、环保局、规划局、住建委等部门进行的项目审批信息及进展,属于前期项目。
2.根据该项目的描述,可依据自身条件进行选择和跟进,避免错过。
3.即使该项目已建设完毕或暂缓建设,也可继续跟踪,项目可能还有其他相关后续工程与服务。
400-688-2000