| **** | 建设单位代码类型:|
| 911********58305X7 | 建设单位法人:石广 |
| 董行 | 建设单位所在行政区划:**自治区**市**区 |
| **区**路13号 |
| ****集团四子王100万千瓦风储项目接网工程 | 项目代码:|
| 建设性质: | |
| 2021版本:161-输变电工程 | 行业类别(国民经济代码):D4420-D4420-电力供应 |
| 建设地点: | **自治区**市** |
| 经度:111.97743,111.97737,111.97666,111.97577,111.9864,111.99166,111.99946,112.01149,112.01787,112.01922,112.01845,112.02546,112.04643,112.05126,112.05657,112.05929,112.06686,112.07965,112.08222,112.08648,112.08952,112.08553,112.08275,112.08372,112.08358,112.08185,112.07158,112.06541,112.05872,112.05269,112.04152,112.0266,112.01517,112.00561 纬度: 41.93007,41.93039,41.93041,41.9273,41.90971,41.9008,41.85875,41.83094,41.81611,41.81311,41.81219,41.79388,41.75542,41.73519,41.71193,41.69987,41.66743,41.62745,41.61455,41.613,41.60818,41.59781,41.59695,41.59633,41.59295,41.58926,41.58579,41.58124,41.57212,41.56624,41.55062,41.53652,41.51973,41.51289 | ****机关:****生态环境厅 |
| 环评批复时间: | 2023-06-07 |
| 内环表〔2023〕144号 | 本工程排污许可证编号:无 |
| 项目实际总投资(万元): | 9200 |
| 77.34 | 运营单位名称:**** |
| 911********58305X7 | 验收监测(调查)报告编制机构名称:******公司 |
| ****0191MA1YNWMG3B | 验收监测单位:**科环世纪电磁****公司 |
| 911********7892675 | 竣工时间:2024-08-15 |
| 调试结束时间: | |
| 2025-09-15 | 验收报告公开结束时间:2026-02-06 |
| 验收报告公开载体: | https://gongshi.****.com/h5public-detail?id=475554 |
| **+改扩建 | 实际建设情况:**+改扩建 |
| 无变化 | 是否属于重大变动:|
| ①**花500kV变电站220kV间隔扩建工程:本期扩建220kV出线1回,至四子王100万千瓦风储项目1#220kV升压站,占用预留出线间隔,不新增占地。 ②**2#升压站-1#升压站段220kV输电线路:起于2#220kV升压站,止于1#220kV升压站。线路长度12.4km,立单回路铁塔37基,全线采用单回路架空架设,导线选用2×JL/G1A-400/35钢芯铝绞线。 ③**1#升压站-**花变段220kV输电线路:起于1#升压站,止于**花500kV变220kV间隔。线路长度40.5km,立铁塔125基,除**花变终端塔外其余采用单回路架空架设,导线选用4×JL/G1A-400/35钢芯铝绞线。 | 实际建设情况:①**花500kV变电站(运行名称“红梁变”)220kV间隔扩建工程:本期建设220kV出线1回,至四子王100万千瓦风储项目1#220kV升压站,占用预留出线间隔,不新增占地。 ②**2#升压站-1#升压站段220kV输电线路(220kV堂村线):起于四子王100万千瓦风储项目2#升压站,止于1#升压站。线路长度11.968km,采用单回路架空架设,导线选用2×JL/G1A-400/35钢芯铝绞线,**铁塔34基。 ③**1#升压站-**花变段220kV输电线路(220kV堂红线):起于**花500kV变电站,止于四子王100万千瓦风储项目1#升压站。线路长度38.964km,除**花变终端塔外其余采用单回路架空架设,导线选用4×JL/G1A-400/35钢芯铝绞线,全线共建铁塔112基。 |
| 线路部分优化调整,长度减少。 | 是否属于重大变动:|
| 无 | 实际建设情况:无 |
| 无 | 是否属于重大变动:|
| 及时对施工线路沿线临时占地开展植被恢复工作。沿线施工垃圾应及时清理。线路架设高度应满足环评 | 实际建设情况:线路沿线开展了植被恢复工作,效果良好。沿线施工垃圾无遗留的情况,线路架设高度均满足环评阶段预测的达标高度。 |
| 无 | 是否属于重大变动:|
| 无 | 实际建设情况:无 |
| 无 | 是否属于重大变动:|
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | / |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | / |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | / |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | / |
| 0 | 0 | 0 | 0 | 0 | 0 | 0 | / |
| 1 | 及时清理施工垃圾 | 施工垃圾均已清理,线路沿线土石方已就地平衡。 |
| 1 | 对项目临时占地及时开展植被恢复。 | 输电线路沿线塔基施工区、牵张场、施工便道等临时占地均已采取了植被恢复措施,效果良好。 |
| ****电站扩建出线间隔 | 验收阶段落实情况:****电站扩建出线间隔 |
| / |
| 无 | 验收阶段落实情况:无 |
| / |
| 无 | 验收阶段落实情况:无 |
| / |
| 及时开展临时占地的植被恢复。 | 验收阶段落实情况:项目沿线临时占地均已采取了植被恢复措施,效果良好。 |
| / |
| 无 | 验收阶段落实情况:无 |
| / |
| 无 | 验收阶段落实情况:无 |
| / |
| / |
| / |
| / |
| / |
| / |
| / |
| 1 | 未按环境影响报告书(表)及其审批部门审批决定要求建设或落实环境保护设施,或者环境保护设施未能与主体工程同时投产使用 |
| 2 | 污染物排放不符合国家和地方相关标准、环境影响报告书(表)及其审批部门审批决定或者主要污染物总量指标控制要求 |
| 3 | 环境影响报告书(表)经批准后,该建设项目的性质、规模、地点、采用的生产工艺或者防治污染、防止生态破坏的措施发生重大变动,建设单位未重新报批环境影响报告书(表)或环境影响报告书(表)未经批准 |
| 4 | 建设过程中造成重大环境污染未治理完成,或者造成重大生态破坏未恢复 |
| 5 | 纳入排污许可管理的建设项目,无证排污或不按证排污 |
| 6 | 分期建设、分期投入生产或者使用的建设项目,其环境保护设施防治环境污染和生态破坏的能力不能满足主体工程需要 |
| 7 | 建设单位因该建设项目违反国家和地方环境保护法律法规受到处罚,被责令改正,尚未改正完成 |
| 8 | 验收报告的基础资料数据明显不实,内容存在重大缺项、遗漏,或者验收结论不明确、不合理 |
| 9 | 其他环境保护法律法规规章等规定不得通过环境保护验收 |
| 不存在上述情况 | |
| 验收结论 | 合格 |