| 1 | 凿毛 | m2 | 286.66 | 55.00 | |
| 2 | C35混凝土材料及浇筑费 | m3 | 13.97 | 1,265.00 | |
| 3 | 模板材料、制作及拆除费 | m2 | 79.13 | 220.00 | |
| 4 | 脚手架材料、搭设及拆除费 | m2 | 313.50 | 44.00 | |
| 5 | 钢筋三级钢φ8 | KG | 688.31 | 10.45 | |
| 6 | 钢筋三级钢φ20 | KG | 1,255.35 | 10.45 | |
| 7 | 植筋三级钢φ8 | 根 | 1,104.00 | 8.80 | |
| 8 | 植筋三级钢φ16 | 根 | 8.00 | 38.50 | |
| 9 | 植筋三级钢φ18 | 根 | 24.00 | 49.50 | |
| 10 | 植筋三级钢φ20 | 根 | 64.00 | 60.50 | |
| 11 | 焊接三级钢φ8 | 根 | 1,344.00 | 5.50 | |
| 12 | 开浇筑孔0.2*0.1m | 个 | 48.00 | 55.00 | |
| 13 | 浇筑漏洞混凝土 | m3 | 1.13 | 1,265.00 | |
| 14 | 基层清理 | m2 | 21.42 | 33.00 | |
| 15 | 粘钢4mm,Q355B | m2 | 19.43 | 990.00 | |
| 16 | 粘钢6mm,Q355B | m2 | 19.18 | 1,045.00 | |
| 17 | 角钢L100*5 | 元 | 2.70 | 198.00 | |
| 18 | 化学锚栓M10 | 套 | 578.00 | 8.80 | |
| 19 | 化学锚栓M16 | 套 | 24.00 | 16.50 | |
| 20 | **扩大拆除 | 项 | 1.00 | 1,100.00 | |
| 21 | 化学锚栓M8 | 套 | 162.00 | 6.60 | |
| 22 | 钢筋三级钢φ6 | kg | 197.81 | 11.55 | |
| 23 | 钢筋三级钢φ10 | kg | 206.02 | 10.45 | |
| 24 | 钢筋三级钢φ12 | kg | 621.19 | 10.45 | |
| 25 | 植筋三级钢φ6 | 根 | 180.00 | 6.60 | |
| 26 | 植筋三级钢φ10 | 根 | 254.00 | 11.00 | |
| 27 | 植筋三级钢φ12 | 根 | 526.00 | 16.50 | |
| 28 | 粘钢3mm | m2 | 3.38 | 935.00 | |
| 29 | 穿梁螺杆φ16 | 根 | 33.00 | 55.00 | |
| 30 | 楼板剔槽 | m | 519.08 | 33.00 | |
| 31 | 钢梁HW200*200,Q235B | kg | 833.33 | 13.20 | |
| 32 | 化学锚栓M20 | 套 | 16.00 | 66.00 | |
| 33 | 楼板开洞 1.2*1.05m | 个 | 2.00 | 880.00 |
| 1 | 人工费支付采用按月支付,在合同工期内,按实际出勤人数,按月拨付至农民工工资专户(发包人向专用账户支付的农民工工资仍为工程款的一部分。) |
| 2 | 工程竣工结算审定后三个月内或竣工结算审定当年年底,拨付劳务分包人工程款至97%(随工程建设方拨付工程款实际情况推进)。 |
| 3 | 余款留作质量保修金,,按照工程承包,人与发包,人签订的《建设工程施工合同》中有关保修金条款中约定的保修期执行。 |